The steps
- Referral. Under FAR 9.406-3(a) and 9.407-3(a), each agency must have procedures for promptly reporting, investigating and referring matters to its suspending and debarring official.
- Sometimes, a pre-notice letter. The official may first write to the contractor without excluding it. FAR 9.403 calls this a pre-notice letter, issued at the official's discretion, and says it is not a mandatory step.
- The notice. A suspension takes effect when issued. A debarment starts with a notice of proposed debarment, which also excludes from the day it is issued. Under FAR 9.406-3(c) it goes to the contractor and each named affiliate. See what the notice must say.
- 30 days to respond. The contractor may submit information and argument in opposition within 30 days of receiving the notice. A general denial isn't enough to raise a genuine dispute over the facts.
- Fact-finding, if the facts are disputed. In an action not based on a conviction or civil judgment, a genuine dispute over material facts entitles the contractor to appear with counsel, submit documents, present witnesses and confront the agency's witnesses, with a transcribed record.
- The decision. For a debarment with no genuine dispute, or one based on a conviction or civil judgment, FAR 9.406-3(d)(1) asks for a decision within 45 days of the record closing, extendable for good cause. Without a conviction, the cause must be established by a preponderance of the evidence. The contractor gets prompt written notice, with the period of debarment.
A cause doesn't mean an exclusion
FAR 9.406-1(a) says the existence of a cause for debarment doesn't necessarily require debarment. The official weighs the seriousness of what happened against remedial measures and mitigating factors, and the rule lists them: among others, whether the contractor had effective standards of conduct and internal controls, disclosed the problem to the government in time, investigated fully and shared the results, cooperated, paid restitution, disciplined the people responsible and put new controls and training in place. On the other side: a pattern of wrongdoing, how widespread it was, whether principals tolerated it, and prior exclusions or administrative agreements.
The contractor carries the burden of showing that it is presently responsible.
Administrative agreements
Many cases end in an administrative agreement instead of a debarment. FAR 9.403 defines it as an agreement between the suspending and debarring official and the contractor that resolves a suspension or debarment proceeding, or a potential one. An agreement doesn't appear as an exclusion, but a prior one is a factor the official weighs if trouble comes back.
What a prime should watch for
- The middle of the process already counts. A suspended or proposed-for-debarment sub is restricted the day the record takes effect, and in SAM.gov it shows as Ineligible (Proceedings Pending). Don't wait for the outcome.
- Affiliates are named. The notice goes to each affiliate the agency names, and a debarment can reach them. Check a sub's sister companies when it is hit.
- A record can end early. A suspension that ends, or a debarment the official declines, removes the restriction. Re-check rather than relying on what you saw once.
- The sub has to tell you. Under FAR 52.209-6, a sub over the threshold discloses in writing whether it or its principals are excluded.
Watch re-checks every confirmed supplier against SAM.gov's exclusions daily, and within about 15 minutes of each load; an exclusion linked by UEI or CAGE becomes a finding. See how exclusion monitoring works.