What a CPSR is, and who gets one
FAR 44.301 gives the objective: to evaluate the efficiency and effectiveness with which the contractor spends government funds and complies with government policy when subcontracting. The review gives the administrative contracting officer (ACO) a basis for granting, withholding or withdrawing approval of the purchasing system.
- The trigger. Under FAR 44.302, the ACO decides whether a CPSR is needed from the contractor's past performance and the volume, complexity and dollar value of its subcontracts. If sales to the government are expected to exceed $25 million in the next 12 months, the ACO performs a review to determine whether one is needed. For DoD, DFARS 244.302 uses $50 million in place of that figure.
- What counts as sales. Prime contracts, subcontracts under government prime contracts, and modifications. Competitively awarded firm-fixed-price contracts, competitively awarded fixed-price contracts with economic price adjustment, and sales of commercial supplies and services under FAR part 12 are left out of the FAR figure.
- How often. Once the first determination is made, the ACO decides at least every three years whether another review is necessary.
- The system, not one contract. Generally a CPSR is not performed for a specific contract.
This guide is written from the FAR and DFARS as posted on acquisition.gov on November 15, 2026. It doesn't describe a reviewing agency's internal guidebook, questionnaires or sampling practice, which we could not read from the official source; ask your ACO or the review team for the current version of those. This is general information, not legal advice, and this area is moving. The clause in your contract is the one that binds you.
What the review looks at
FAR 44.303 has the review evaluate the purchasing system, including policies, procedures and performance, using the same considerations a contracting officer uses when consenting to a subcontract (FAR 44.202-2). It names eleven areas for special attention:
- The results of market research
- The degree of price competition obtained
- Pricing policies and techniques, including how certified cost or pricing data is obtained
- Methods of evaluating subcontractor responsibility, including the contractor's use of the SAM Exclusions and, if it has subcontracts with parties on the Exclusions list, the documentation, systems and procedures it set up to protect the government's interests
- Treatment of affiliates and other concerns with close working arrangements with the contractor
- Policies and procedures on small business concerns
- Planning, award and postaward management of major subcontract programs
- Compliance with Cost Accounting Standards in awarding subcontracts
- Appropriateness of the types of contracts used
- Management control systems, including internal audit procedures, for progress payments to subcontractors
- Implementation of higher-level quality standards
Unless they can't practically be separated, subcontracts awarded exclusively in support of competitively awarded firm-fixed-price contracts, competitively awarded fixed-price contracts with economic price adjustment, or part 12 commercial contracts are left out of the evaluation. For DoD, DFARS 244.303 adds two things: the rationale behind commercial product and commercial service determinations, and the counterfeit electronic part detection and avoidance system.
The DoD criteria: DFARS 252.244-7001
For DoD contracts, DFARS 252.244-7001 (dated January 2025 when checked) makes an acceptable purchasing system a contract duty and lists 24 system criteria. It goes in contracts that contain FAR 52.244-2, Subcontracts. The criteria nearest to supplier screening and flow-down:
- (c)(2) Ensure that all applicable purchase orders and subcontracts contain all flowdown clauses, including terms and conditions and any other clauses needed to carry out the requirements of the prime contract.
- (c)(5) Establish and maintain adequate documentation to provide a complete and accurate history of purchase transactions to support vendors selected and prices paid.
- (c)(7) Use competitive sourcing to the maximum extent practicable, and ensure debarred or suspended contractors are properly excluded from contract award.
- (c)(18) Perform internal audits or management reviews, training, and maintain policies and procedures for the purchasing department to ensure the integrity of the purchasing system.
- (c)(19) Establish and maintain policies and procedures to ensure purchase orders and subcontracts contain mandatory and applicable flowdown clauses, as required by the FAR and DFARS.
Under DFARS 244.305-70 the contracting officer, in consultation with the purchasing system analyst or auditor, measures the system against these criteria. A failure that amounts to a material weakness starts a clock: an initial written determination, 30 days for the contractor to respond, a final determination, then 45 days to correct the weakness or submit an acceptable corrective action plan. If material weaknesses remain, the system is disapproved.
What approval is worth
- Consent. Without an approved purchasing system, FAR 52.244-2 requires the contracting officer's consent for cost-reimbursement, time-and-materials and labor-hour subcontracts, and for fixed-price subcontracts above the levels the clause sets. A notice of approval (FAR 44.305-2) waives the consent requirement in fixed-price contracts and for specified subcontracts in cost-reimbursement contracts, though the contracting officer can still name subcontracts that need it.
- Payment. If the system is disapproved and the contract includes DFARS 252.242-7005, Contractor Business Systems, the contracting officer withholds 5 percent of amounts due from progress payments and performance-based payments, and directs the same on interim cost vouchers, until the weaknesses are corrected. An acceptable corrective action plan being carried out brings it to 2 percent. The cap is 5 percent for one business system and 10 percent across several. That clause applies only to covered contracts subject to the Cost Accounting Standards.
- Withdrawal. The ACO may withdraw approval at any time on a determination that the system has deteriorated, or to protect the government's interest (FAR 44.305-3).
The exclusion-check evidence
Four texts point at the same file:
- FAR 9.405-2(c): the contractor's compliance with 52.209-6 will be reviewed during Contractor Purchasing System Reviews.
- FAR 44.303(d): the review gives special attention to the contractor's use of the SAM Exclusions, and to what it did when it subcontracted with a party on the list.
- FAR 44.202-2(a)(13): is the proposed subcontractor listed as excluded in the System for Award Management?
- DFARS 252.244-7001(c)(7): ensure debarred or suspended contractors are properly excluded from contract award.
Read together, they ask you to be able to show, for a subcontract or purchase order picked from your records:
- That you checked the right company. The UEI or CAGE code you searched, and how you knew it was the supplier on the order. A name search alone leaves this open: see how to check if a company is debarred.
- When you checked, against what. The date of the check and the date of the exclusions data, close to the award and not only at onboarding.
- What came back. Including possible name matches, who decided each one was or wasn't the supplier, and why.
- The sub's written disclosure. For subcontracts over $45,000 that aren't for COTS items, 52.209-6 requires the sub to state in writing whether it or its principals are excluded.
- If you used an excluded party. The written notice to the contracting officer, the compelling reason, and the systems and procedures you put in place.
- That it is a system. The written procedure that says who checks, when, and what is kept, and evidence that it is followed between reviews: criterion (c)(18) expects internal reviews of your own.
The list is our reading of those four texts, not a reviewer's checklist. The pre-award checklist lays out the same file step by step.
The flow-down evidence
Criteria (c)(2) and (c)(19) ask for two things: subcontracts that contain the right clauses, and policies and procedures that make that happen. In a file, that is:
- The prime contract's clauses, and the list of those that flow down to this kind of subcontract
- For a commercial product or service, the shorter list in FAR 52.244-6, and the determination that the item is commercial, which DFARS 244.303(a) has the review test
- The subcontract or purchase order as issued, showing the clauses it carried
- The representations and certifications you collected from the sub, signed and dated
- The procedure that tells a buyer how to build the clause list, and who reviews it
Clause numbers are moving under the FAR Overhaul, so record which version of the FAR each prime contract is under. The Section 889 guide shows one rule under three numbers.
Status under the FAR Overhaul (checked November 15, 2026)
| Topic | FAR and DFARS as codified | Overhaul deviation text and proposed rule (FAR Case 2026-003) |
|---|---|---|
| Where it sits | FAR subpart 44.3, sections 44.301 to 44.307 | Subpart 44.3 "Postaward", section 44.301 |
| Trigger | Review whether a CPSR is needed when sales are expected to exceed $25 million | No dollar figure: the contracting officer decides from factors such as past performance and the volume, complexity and dollar value of subcontracts |
| Every three years | ACO decides whether a review is necessary | Kept |
| Areas for special attention | The eleven in 44.303, including use of the SAM Exclusions | The list is not in the text |
| 52.209-6 compliance | Reviewed in CPSRs (9.405-2(c)) | Kept in the Part 9 deviation text and in the Part 9 proposed rule |
| Approval, withholding, withdrawal | 44.305 | Kept, at 44.301-3 to 44.301-5 |
The Part 44 proposed rule was published September 18, 2026 with comments due October 19, 2026, and its preamble says it would not substantively change the policies and procedures of the part. We found no final rule. The DFARS sections and clauses above are quoted as posted with DFARS Change 05/07/2026, and DFARS 244.302 still sets its $50 million figure "in lieu of the threshold at FAR 44.302(a)". Even where the FAR list of review areas goes away, the DFARS criteria on excluded parties and flow-down are in the contract clause itself. See also the FAR Overhaul guide.
How Watch helps you answer
- The right company. You confirm each supplier's SAM.gov registration once. An exact UEI or CAGE on your list confirms by itself; a name never does. Who confirmed it, and when, is recorded.
- Dated checks. Exclusions are loaded daily and each supplier is re-checked on a schedule. Every check keeps what the list said and its data date.
- A check before the award. A watch with a deadline re-checks its suppliers the day before and freezes the result as a dated snapshot with a SHA-256.
- Decisions. A name-only match is shown as "possible, confirm" and never decided by Watch. The person who decides it, and their note, go in the audit log.
- Something to hand over. The audit log is append-only and hash-chained. You can open a supplier as it stood on a past date, export a list's evidence as CSV or JSON with a source and data date on every fact, or produce a PDF evidence package for one supplier.
- The supplier's side of flow-down. Signed questionnaires and uploaded documents kept on the supplier, requirements per contract tag, and a printable flow-down pack per tag.
Watch covers the supplier-screening part of a purchasing system only. It doesn't do price analysis, competition records, consent packages or make-or-buy, it doesn't check which clauses are in a subcontract, and it tracks companies, never individuals, so a principal named in a disclosure is checked at SAM.gov. It doesn't prepare you for a review or predict its result.